Pembangunan LRT Sudah Capai 65,17 Persen

LRT Construction Has Reached 65.17 Percent

PT. Jakpro President Director, Satya Heragandhi disclosed, the Light Rail Transit (LRT) construction in the capital has reached 65.17 percent.

The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games

The development progress includes the construction of the P102 package project or the main construction package that reaches 65%. Further, the work of P103 package in the form of train procurement that reaches 61% and operational planning (Operational Plan) has reached 45%.

Jakpro Optimists to Test LRT on Schedule

"The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games," he expressed, Friday (3/30).

He explained, LRT Jakarta has 6 stations, namely Depot Station, Kelapa Gading Mall, Kelapa Gading Boulevard, Pulomas, Pacuan Kuda, and Velodrome. 

"Eventually those stations will be connected with venue locations, Transjakarta bus lanes and east-west MRT station," he stated.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye745 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye544 personAldi Geri Lumban Tobing
  3. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye535 personAnita Karyati
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye517 personFakhrizal Fakhri
  5. Jakarta Logs 0.13% Inflation as Chicken, Chili, and Rice Push Prices Up

    access_time03-10-2026 remove_red_eye501 personFakhrizal Fakhri