Pembangunan LRT Sudah Capai 65,17 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

LRT Construction Has Reached 65.17 Percent

PT. Jakpro President Director, Satya Heragandhi disclosed, the Light Rail Transit (LRT) construction in the capital has reached 65.17 percent.

The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games

The development progress includes the construction of the P102 package project or the main construction package that reaches 65%. Further, the work of P103 package in the form of train procurement that reaches 61% and operational planning (Operational Plan) has reached 45%.

Jakpro Optimists to Test LRT on Schedule

"The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games," he expressed, Friday (3/30).

He explained, LRT Jakarta has 6 stations, namely Depot Station, Kelapa Gading Mall, Kelapa Gading Boulevard, Pulomas, Pacuan Kuda, and Velodrome. 

"Eventually those stations will be connected with venue locations, Transjakarta bus lanes and east-west MRT station," he stated.

Linked News
Popular News indeks
  1. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye314 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye311 personDessy Suciati
  3. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye293 personAldi Geri Lumban Tobing
  4. 19,675 People Visit Ragunan Zoo on Islamic New Year

    access_time27-06-2025 remove_red_eye286 personTiyo Surya Sakti
  5. Transjakarta Wins Award for Best GCG Company

    access_time27-06-2025 remove_red_eye271 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik